WORKDAY function
the serial number of the date before or after a specified number of workdays.
Date and time
Where can you use it?
Planning and operations teams. Use this group to work with dates and times in calendars, delivery schedules, shifts and period reporting.
Scenario in the workbook
Move a deadline by working days. The next workday after the start counts as day one.
A worked example from the workbook
| Row | A | B |
|---|---|---|
| 6 | Input | Comparison |
| 7 | 46023 | 1 |
| 8 | 46023 | 2 |
| 9 | 46023 | -1 |
Record 1
=WORKDAY(A7,B7)Expected result46024
See the inputs and instructions for all 3 examplesSyntax
WORKDAY(start_date, days, [holidays])
Copyable formulas
English Excel · en-US
=WORKDAY(A7,B7)Turkish Excel · tr-TR
=İŞGÜNÜ(A7;B7)Worked examples
Move a deadline by working days. The next workday after the start counts as day one.
Open the English sheet. Inputs begin at A6. F7:F9 show the live results and G7:G9 show the original results for comparison.
| Row | A | B |
|---|---|---|
| 6 | Input | Comparison |
| 7 | 46023 | 1 |
| 8 | 46023 | 2 |
| 9 | 46023 | -1 |
| Case | Formula | Expected result |
|---|---|---|
| Record 1 | =WORKDAY(A7,B7) |
46024 |
| Record 2 | =WORKDAY(A8,B8) |
46027 |
| Record 3 | =WORKDAY(A9,B9) |
46022 |